Completion Rate in Sewage Network Project in Al Musanaa Reaches 78pc
Al musanaa: The execution rate of the project to complete the sewage network, treatment plant, and irrigation pipeline in the Wilayat of Al Musanaa, South Al Batinah Governorate, has reached 78%. The total cost of the project is RO 9.877 million, covering all its facilities and components. According to Oman